ARTICLE
5 October 2018

Force Majeure Best Practices – Hurricane Florence Edition

FL
Foley & Lardner

Contributor

Foley & Lardner LLP looks beyond the law to focus on the constantly evolving demands facing our clients and their industries. With over 1,100 lawyers in 24 offices across the United States, Mexico, Europe and Asia, Foley approaches client service by first understanding our clients’ priorities, objectives and challenges. We work hard to understand our clients’ issues and forge long-term relationships with them to help achieve successful outcomes and solve their legal issues through practical business advice and cutting-edge legal insight. Our clients view us as trusted business advisors because we understand that great legal service is only valuable if it is relevant, practical and beneficial to their businesses.
The threat presented by Hurricane Florence has forced government officials to order South Carolina residents to evacuate hurricane zones.
United States Corporate/Commercial Law
To print this article, all you need is to be registered or login on Mondaq.com.

The threat presented by Hurricane Florence has forced government officials to order South Carolina residents to evacuate hurricane zones. Safety should always be the No. 1 priority for the millions of individuals and families affected by the storm. The mandatory evacuation and closure of many businesses and schools in the area has shut down a number of manufacturing facilities and distributors located in South Carolina.

For manufacturing suppliers located in South Carolina and others in the supply chain impacted by these shutdowns, companies should look at their contracts to determine "force majeure" rights and requirements. Force majeure refers to circumstances beyond a party's control that prevent the party from fulfilling its obligations under a contract. Common force majeure provisions may cover several categories of events that could impact suppliers and customers across the supply chain. These provisions often include a list of natural disasters or "acts of God," including hurricanes.

Any party seeking to invoke the force majeure provision should be able to show that there are no alternative means for delivering parts under the contract. Increased costs alone will not be sufficient to prevail on a claim of force majeure. For example, if a company is able to ship parts from a different manufacturing facility, even if that requires running extra shifts, paying employees overtime and/or expedited freight, then it will be very difficult to show that it was unable to perform under the contract.

Here are some best practices for a company to follow when seeking to invoke the force majeure provision of a contract or when a customer receives a force majeure notice:

  1. Review the contract's exact force majeure provision to determine what is allowed and whether the covered event is listed;
  2. Confirm that the notice requirements have been met;
  3. Provide or obtain as much information about the specific force majeure claim as possible, including the timing, the number of impacted parts/facilities, and when the force majeure event is expected to conclude;
  4. The parties should work together to assess parts on hand, whether there is a bank of parts that can be accessed, whether there are other manufacturing lines available at different locations, the affected supplier's allocation plan (note: a commercially reasonable allocation across customers is required), and whether and when an alternate supplier can be ramped up;
  5. Be aware of the other party's rights if force majeure is invoked, which may include the right to terminate and source from an alternate supplier or to terminate after a certain period of time; and
  6. Look across your supply chain to determine whether a sub-supplier's force majeure notice triggers a force majeure event requiring that notice be provided to your customers.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More