ARTICLE
13 February 2015

Force Majeure Clauses: An "Out" For Suppliers Facing Shortages And Supply Chain Disruptions From West Coast Labor Dispute

FL
Foley & Lardner

Contributor

Foley & Lardner LLP looks beyond the law to focus on the constantly evolving demands facing our clients and their industries. With over 1,100 lawyers in 24 offices across the United States, Mexico, Europe and Asia, Foley approaches client service by first understanding our clients’ priorities, objectives and challenges. We work hard to understand our clients’ issues and forge long-term relationships with them to help achieve successful outcomes and solve their legal issues through practical business advice and cutting-edge legal insight. Our clients view us as trusted business advisors because we understand that great legal service is only valuable if it is relevant, practical and beneficial to their businesses.
With the ongoing West Coast labor dispute and increasing port congestion causing gridlock, suppliers should look to their contracts to determine whether they have the right to declare force majeure with their customers.
United States Corporate/Commercial Law
To print this article, all you need is to be registered or login on Mondaq.com.

With the ongoing West Coast labor dispute and increasing port congestion causing gridlock, suppliers should look to their contracts to determine whether they have the right to declare force majeure with their customers in the event of a supply chain disruption caused by the labor dispute. If there is a force majeure provision in the parties' supply contract that covers labor disputes, then the supplier should determine what rights and obligations it has under that provision.

Force majeure refers to unforeseeable circumstances that prevent a party from fulfilling a contract. Common force majeure provisions may cover several categories of events that could impact the supply chain. The provision may cover risks that are reasonably beyond the control of the party claiming force majeure. Specific events that the provision may cover include: (a) natural disasters or "acts of God," such as lightening, tornadoes, hurricanes, tsunamis, floods and earthquakes; (b) manmade disasters, such as plant fires or floods; (c) war and civil issues, such as riots, civil unrest, acts of terrorism; (d) labor disputes or strikes; (e) government embargoes or other government actions affecting the supply chain; and even (f) power outages or transportation issues.

It is important to note that even if a listed event occurs, the party seeking to invoke the force majeure provision must be able to show that there are no alternative means, increased costs notwithstanding, for fulfilling the contract. The event has to be one that prevents performance at virtually all costs. For example, if the supplier is able to timely deliver parts by using expedited air freight, even though this form of transportation is more expensive, the supplier likely will not be able to rely on the force majeure provision to suspend performance under the supply contract.

A well-drafted force majeure provision should include two key elements. First, the provision should define the events that constitute a force majeure. Second, the provision should set forth the supplier's rights and obligations if a force majeure event occurs that impacts the supplier's ability to timely supply parts. Both the defined force majeure events and their operative effect will depend upon the products at issue, the regions involved in the supply chain and risk allocation between the parties.

As a practical matter, when drafting a force majeure provision for a specific supply agreement or to include in a party's standard terms and conditions, the contracting party should consider each of the events that it has defined as force majeure events and how it will deal with each event if it occurs. If the operative effect of the force majeure event is suspension of the supplier's performance, the provision should spell out for how long the performance will be suspended. Some provisions will suspend performance until the event giving rise to the force majeure is over. Other provisions will suspend performance for a defined period of time and provide the parties the right to terminate the contract if performance has not resumed by the end of that time period. However, the provision may allow only the customer to terminate the contract in the event that the supplier suspends performance pursuant to force majeure. Finally, most force majeure provisions contain a notice requirement that obligates the supplier to provide its customer prompt notice of the event giving rise to the force majeure and the expected duration of the issue.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.