Throughout our Firm’s history, Lewis Rice attorneys have made excellence the foundation of our practice. More than a century of service, since our founding in 1909 in downtown Saint Louis by Joseph Lewis and Charles Rice, gives us the experience, reputation, resources, and vision to serve our clients’ dynamic needs. We provide sophisticated legal counsel and custom-tailored solutions for the challenges facing local, regional, and national businesses.
On April 12, 2016, the Missouri Court of Appeals held, for the first time, that contractors who have performed work for shopping mall tenants may have mechanic's lien rights on the entire mall if the tenant fails to pay.
United States Real Estate and Construction
To print this article, all you need is to be registered or login on Mondaq.com.

On April 12, 2016, the Missouri Court of Appeals held, for the first time, that contractors who have performed work for shopping mall tenants may have mechanic's lien rights on the entire mall if the tenant fails to pay. The case, Crafton Contracting Co. v. Swenson Construction Co., gives contractors and subcontractors an opening to more effectively enforce liens for improvements made on mall property.

The Crafton court held that when a mall lease requires a tenant to make improvements "of a substantial and permanent nature" to its retail store, the tenant, in making such improvements, becomes an agent of the mall for purposes of subjecting the mall to a lien. The Crafton court noted that "where the improvements are required and completed under the control of the [mall] owner with the view of improving the property," it is immaterial whether the mall owner ultimately benefits financially from the tenant build out. Applying this reasoning to the facts of Crafton, the court determined that, because Plaza Frontenac Mall supervised and controlled how the improvements were made by tenant Allen Edmonds, pursuant to the terms of the lease granting it such control, the improvements were substantial and permanent, even though the value of the improvements was no more than two percent of the value of the mall. Thus, the court held that the contractors could appropriately enforce their mechanic's liens against Plaza Frontenac Mall.

Click under "Resources" below to read the full opinion.

Contractors and subcontractors are encouraged to promptly contact an attorney if they have any questions regarding their lien rights when facing nonpayment or slow payment from customers.

Resources

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More