Dickinson Wright is a general practice business law firm with more than 475 attorneys among more than 40 practice areas and 16 industry groups. With 19 offices across the U.S. and in Toronto, we offer clients exceptional quality and client service, value for fees, industry expertise and business acumen.
On November 1, 2021, the environmental committee of ASTM International approved revisions to the organization's E1527 standard practice for Phase I environmental site assessments.
United States Environment
To print this article, all you need is to be registered or login on Mondaq.com.

On November 1, 2021, the environmental committee of ASTM International approved revisions to the organization's E1527 standard practice for Phase I environmental site assessments.1  The ASTM standard is widely used to satisfy the "All Appropriate Inquiries" (AAI) requirements under U.S. Environmental Protection Agency (U.S. EPA) rules2 that allow parties of commercial property transactions to establish certain defenses to liability under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). Many jurisdictions have also incorporated some or all of these requirements into defenses and exemptions relating to state liability for hazardous waste contamination.

The revised ASTM standard is not expected to be published until December 2021. U.S. EPA's rules currently refer to the 2013 version of the standard, E1527-13, and it is likely that the agency will allow for a transition period in substituting a requirement to utilize the 2021 version, as it has in the past.3 However, those engaging in real estate transactions should be aware that these changes are coming. The key revisions include:

  • Clarification of the terms  "Recognized Environmental Condition" (REC); "Controlled Recognized Environmental Condition" (CREC); and "Historical Recognized Environmental Condition (HREC) with an appendix providing guidance and examples of each category;
  • Addition of more detailed site reconnaissance requirements;
  • Provision of a formal definition of a "significant data gap" that might prevent identification of a REC; and
  • Updated discussion of emerging contaminants such as per- and polyfluoroalkyl substances (PFAS) as a business environmental risk or non-scope consideration as part of a set of revised appendices.

This final item is particularly important since questions about the appropriate consideration of potential PFAS contamination have become an increasing concern in property transactions in recent years.  Still, this is also an evolving area given that U.S. EPA's recently published "PFAS Strategic Roadmap" states that the agency intends to finalize a rule designating certain PFAS chemicals as hazardous substances under CERCLA by summer 2023, which would bring those chemicals within the scope of the ASTM standard.4

Footnotes

1 https://newsroom.astm.org/astm-international-revises-standard-practice-environmental-site-assessments

2 40 CFR Part 312.

3 79 Fed. Reg. 60087 (Oct. 6, 2014) (eliminating regulatory reference to use of ASTM E1527-05 to satisfy the All Appropriate Inquiries requirements effective October 6, 2015, in favor of ASTM E1527-13 which had been finalized in November 2013.

4 https://www.epa.gov/system/files/documents/2021-10/pfas-roadmap_final-508.pdf

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More