Lien And Bond Claims In May 2024: Dates To Remember

GR
Gray Reed & McGraw LLP

Contributor

A full-service Texas law firm with offices in Dallas, Houston and Waco, Gray Reed provides legal services to companies ranging from start-up to Fortune 100 as well as high net worth individuals. For more information, visit www.grayreed.com.
Use this guide as a reference when filing lien and bond claim notices for the month of May. If you have any questions about the lien and bond claim process...
United States Texas Real Estate and Construction

Use this guide as a reference when filing lien and bond claim notices for the month of May. If you have any questions about the lien and bond claim process, don't hesitate to reach out to any member of the Gray Reed Construction Practice Group.

Lien and Bond Claim Notices and Filings Required by: May 15, 2024
Texas Property Code Chapter 53
Notice of Intent to Lien for Subs/Suppliers of All Tiers for Work/Materials Furnished During: February 2024
Liens Filed by Original Contractors and Subs/Suppliers of All Tiers for Work/Materials Furnished During: January 2024
Texas Government Code Chapter 2253
Notice of Unpaid Claim for Subs/Suppliers of All Tiers for Work/Materials to GC Furnished During: March 2024
Notice of Unpaid Claim for Subs/Suppliers of All Tiers for Work/Materials to GC and Surety Furnished During: February 2024
Residential
Notice of Intent to Lien for Subs/Suppliers of All Tiers for Work/Materials Furnished During: March 2024
Liens Filed by Original Contractors and Subs/Suppliers of All Tiers for Work/Materials Furnished During: February 2024


The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More