At Memery Crystal, every action is thoughtfully considered. Since 1978, we’ve been a leading UK law firm known for intelligent, incisive, and inventive thinking. We are commercially aware, entrepreneurial, and pragmatic, regularly cited in Chambers UK and The Legal 500. In 2021, we joined RBG Holdings plc.

Our core values are:

Trusted business-focused advisers
Individuality and personal responsibility
Friendly and supportive approach

We champion diversity and encourage our team to share their expertise with chosen charities, donating a percentage of our profits to support their goals.

As of April 25, 2024, planning enforcement periods were amended, extending the immunity period for most breaches of planning control to 10 years for substantial completions occurring on or after this date.
UK Real Estate and Construction
To print this article, all you need is to be registered or login on Mondaq.com.

As of 25 April 2024, planning enforcement periods have been amended by the Planning Act 2008 (Commencement No. 8) and Levelling-Up and Regeneration Act 2023 (Commencement No. 4 and Transitional Provisions) Regulations 2024. Transitional provisions have been included to allow for work where substantial completion took place before 25 April 2024.

These Regulations amend section 171B of the Town and Country Planning Act 1990 so that in most cases, development becomes immune from enforcement if no action is taken:

  • within 10 years of substantial completion for a breach of planning control consisting of operational development where substantial completion took place on or after 25 April 2024.
  • within 10 years for an unauthorised change of use to a single dwellinghouse where the change of use took place on or after 25 April 2024.
  • within 4 years of substantial completion for a breach of planning control consisting of operational development where substantial completion took place before 25 April 2024.
  • within 4 years for an unauthorised change of use to a single dwellinghouse where the change of use took place before 25 April 2024.
  • within 10 years for any other breach of planning control (essentially other changes of use).

It should be noted that the time limits set out above do not prevent enforcement action after the relevant dates in certain circumstances. For example (and in brief):

  • further enforcement action is permitted in respect of any breach of planning control within 4 years of previous enforcement action in respect of the same breach.
  • Where there has been deliberate concealment of a breach of planning control.

Originally published by 29 April, 2024

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More