John Michael Sharp v Sir Maurice Victor Blank [2017] EWHC 3390 (Ch)

CC
Clyde & Co

Contributor

Clyde & Co  logo
Clyde & Co is a leading, sector-focused global law firm with 415 partners, 2200 legal professionals and 3800 staff in over 50 offices and associated offices on six continents. The firm specialises in the sectors that move, build and power our connected world and the insurance that underpins it, namely: transport, infrastructure, energy, trade & commodities and insurance. With a strong focus on developed and emerging markets, the firm is one of the fastest growing law firms in the world with ambitious plans for further growth.
Costs budgets cover costs to be incurred (not costs already incurred). PD3E para 7.6 provides that "Each party shall revise its budget in respect of future costs upwards or downwards...
UK Litigation, Mediation & Arbitration
To print this article, all you need is to be registered or login on Mondaq.com.

Court considers revision of a costs budget and the meaning of a "significant development"

Costs budgets cover costs to be incurred (not costs already incurred). PD3E para 7.6 provides that "Each party shall revise its budget in respect of future costs upwards or downwards, if significant developments in the litigation warrant such revisions ... The court may approve, vary or disapprove the revisions having regard to any significant developments which have occurred since the date when the previous budget was approved or agreed".

This case involved seven claims that were subject to a group litigation order and the claimants applied for a costs management order. Total budgeted costs amounted to just under £37 million. The defendants subsequently asserted that certain significant developments required them to revise their budget and the claimants refused to agree to the revisions.

Chief Master Marsh held that the court has jurisdiction to revise a budget taking the last agreed or approved budget as the base reference point: "Costs which have been incurred since the date of the last agreed or approved budget (or the antecedent date) that relate to significant developments are, for the purposes of revision, placed in the estimated columns of the revised Precedent H in one or more phase. In some cases, it may not be obvious where they go (for example a late application for security for costs) but I can see no reason why Precedent H may not be adapted as necessary to accommodate work that does not easily fit in".

The following factors were found to be "significant developments" in this case: (a) the trial timetable had been extended by a total of 48 business days; (b) an application for specific disclosure had resulted in a large number of documents that had to be reviewed; and (c) the claimants had served an expert's report which was a change from the agreed basis upon which expert evidence was to be provided. However, the following factors were found not to be "significant developments": (a) the claimants' application for third party disclosure; (b) questions put to the defendants' experts by the claimants; and (c) modest adjustments to the claimants' case following a change in approach by the claimants' expert.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More