New Saudi Procurement Law Will Create Favourable Market For Construction Projects In 2020

CC
Clyde & Co

Contributor

Clyde & Co  logo
Clyde & Co is a leading, sector-focused global law firm with 415 partners, 2200 legal professionals and 3800 staff in over 50 offices and associated offices on six continents. The firm specialises in the sectors that move, build and power our connected world and the insurance that underpins it, namely: transport, infrastructure, energy, trade & commodities and insurance. With a strong focus on developed and emerging markets, the firm is one of the fastest growing law firms in the world with ambitious plans for further growth.
2020 begins just a month into the Saudi Government's new Government Tenders & Procurement Law (GTPL), which came into effect on 1 December 2019,...
Saudi Arabia Government, Public Sector
To print this article, all you need is to be registered or login on Mondaq.com.

2020 begins just a month into the Saudi Government's new Government Tenders & Procurement Law (GTPL), which came into effect on 1 December 2019, and government and contractors will be keeping a close eye on how the law works in practice in the market over the next year.

Foremost among the changes in the GTPL, which applies to all appointments by government entities,  are the new provisions for centralised tendering and contracting. These provisions mean a designated Central Entity may request tenders for works it deems to be required by more than one government entity, and engage contractors / consultants on the basis of framework agreements or its own contract forms. This increased focus on centralised processes is designed to promote greater transparency, predictability and efficiency in tendering.

Similarly, the Regulations will lead to better infrastructure outcomes by granting Government Entities greater flexibility to tailor contract conditions (e.g. beyond the Public Works Contract) to particular project requirements.

There are higher maximum delay penalties and new provisions for the termination of contracts by a government entity, and if a project eventually ends up in dispute, the GTPL requires the referral of disputes to the Board of Grievances. However, in a crucial difference to the law it replaces, government entities may agree to arbitration upon approval by the Minister of Finance.

Taken altogether, we predict that 2020 could herald a more favourable market environment for international contractors and consultants seeking to be appointed on government projects. This can only benefit Saudi Arabia's ambitious infrastructure program next year and in the years ahead.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More