Despite the COVID-19 outbreak and the unprecedented impacts the lockdown measures have had on global economic activity, one of the largest infrastructure financing deals to date (~$15bn) was closed.
Mozambique Energy and Natural Resources
To print this article, all you need is to be registered or login on Mondaq.com.

Despite the COVID-19 outbreak and the unprecedented impacts the lockdown measures have had on global economic activity, one of the largest infrastructure financing deals to date (~$15bn) was closed.

Despite the COVID-19 outbreak and the unprecedented shocks to the global economy and to oil markets, Total, the world's seventh-largest oil and gas company, secured approximately $15 billion1 in project financing for the development of a large Liquified Natural Gas ("LNG") plant in Mozambique.

In this article, we present the structure of the recent Mozambique LNG project financing deal, review the main characteristics of infrastructure project financing and finally discuss the different financing alternatives.

Africa's largest project financing deal

Mozambique LNG - development and construction

Following the discovery of large natural gas resources off the coast of northern Mozambique in 2010, a number of major LNG projects were sanctioned for development in Mozambique.2 The Government of Mozambique gave the final approval for the Rovuma Basin Area 1 Mozambique LNG development plan ("Mozambique LNG") in March 2018 which marked the beginning of the development, feasibility studies, pre-construction and construction steps of the infrastructure project (the "Construction Phase").3

Mozambique LNG entails the development of an integrated LNG plant which will include offshore extraction capacities, underwater pipelines, an onshore processing plant and ancillary support facilities.4 The construction of Mozambique LNG began in August 2019.5

To view the full article, please click here.

Footnotes

1. The final financing numbers vary from $14.9 billion to $16 billion.

2. The other major LNG projects sanctioned for development in the country are the Rovuma LNG project and the Coral South FLNG project.

3. Area 1 has approximately 75 trillion cubic feet ("Tcf") of recoverable gas.

4. AFDB, November 2019, Mozambique LNG, Project Summary Notes.

5. https.//www.mzlng.total.com/about-mozambique-liquefied-natural-gas-project

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

ARTICLE
24 November 2020

Project Financing - Review Of Mozambique LNG

Mozambique Energy and Natural Resources
Contributor
FTI Consulting
See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More