The Autorité des marchés publics Assumes Its Responsibilities

DW
Davies Ward Phillips & Vineberg

Contributor

Davies is a law firm focused on high-stakes matters. Committed to achieving superior outcomes for our clients, we are consistently at the heart of their most complex deals and cases. With offices in Toronto, Montréal and New York, our capabilities extend seamlessly to every continent. Visit us at www.dwpv.com.
Previously, the operating rules of the SEAO had been set solely by the secretariat of the Conseil du trésor.
Canada Government, Public Sector
To print this article, all you need is to be registered or login on Mondaq.com.

The majority of the activities of the Autorité des marchés financiers (AMF) under the Act respecting contracting by public bodies were transferred to the Autorité des marchés publics (AMP) on January 25, 2019.

The AMP was created in response to the first recommendation of the Charbonneau Commission after An Act to facilitate oversight of public bodies' contracts and to establish the Autorité des marchés publics was enacted on December 1, 2017.

The first president and CEO of the AMP, Me Denis Gallant, assumed his duties on July 25, 2018 (press release issued in French only). Since then, the AMP has had the mandate to work with the secretariat of the Conseil du trésor to establish the operating rules of the système électronique d'appel d'offres du Gouvernement du Québec (SEAO), the government's online public calls for the tender system. Previously, the operating rules of the SEAO had been set solely by the secretariat of the Conseil du trésor.

On January 25, 2019, the following changes came into effect:

The following additional changes will come into effect on May 25, 2019:

  • Municipalities will be required to publish a notice of intention on the SEAO site 15 days before entering into a contract by mutual agreement with a single supplier for an amount exceeding the threshold established by order.
  • Any interested person or partnership will be able to file a complaint with the AMP about the tendering process for public contracts, the decision made by a public body to award a public contract, or the amendments to the tender documents.
  • The AMP will have the power to suspend, examine and revise a tendering or awarding process for a public contract following a complaint if the public body concerned does not appear to be acting, in respect of the process or contract, in compliance with the normative framework.

It is still too early to determine the impact on the authorization process of the transfer to the AMP of the responsibilities that, until now, had been handled by the AMF. However, the new powers conferred on the AMP could affect the speed of the public contract tendering and awarding processes. During a press conference on January 23, 2019, Me Gallant stated that the call for tenders and awarding processes for public contracts could be slowed down as a result of the provisions regarding complaints to the AMP coming into force on May 25, 2019.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More