Probuild Constructions (AUST) Pty Ltd V Shade Systems Pty Ltd [2016] NSWSC 770

CC
Corrs Chambers Westgarth

Contributor

With over 175 years of experience and a team of over 1000 talented professionals, we offer exceptional legal services for major transactions, projects, and disputes. Our client-focused approach and commitment to excellence ensure success for our clients. We connect with top lawyers globally for the best results.
A recent construction law case considered the issue of judicial review.
Australia Real Estate and Construction
To print this article, all you need is to be registered or login on Mondaq.com.

KEYWORDS: SECURITY OF PAYMENT; JUDICIAL REVIEW KEY TAKEAWAY

In a decision which goes against the long-standing authority in Brodyn Pty Ltd v Davenport, 1 a single Judge of the New South Wales Supreme Court held that judicial review is available to quash an adjudicator's determination for a non-jurisdictional error of law on the face of the record.

This is an interesting result, as it has long been held that judicial intervention into adjudication determinations could only occur in instances of a breach of "the basic and essential requirements" which were "laid down for the existence of an adjudicator's determination". Whether or not future cases will follow this decision remains to be seen.

Note: This decision is also the subject of an "In Brief" on the Corrs website: " The Probuild decision: Finding the balance in construction industry payment".

Facts

Probuild engaged Shade to supply and install external louvres to the façade of an apartment complex in Chatswood. During the course of the work, Shade served a payment claim for $324,334.26. Probuild served a payment schedule which asserted that it would pay Shade nil, as Probuild was entitled to liquidated damages of $1,089,900.

Shade subsequently applied for adjudication of its payment claim. Shade revised its claim down to $214,680.88 in its adjudication application. Probuild continued to rely on its entitlement to liquidated damages in its adjudication response. An adjudicator determined that Probuild owed Shade $277,755.03. Probuild then sought to have the adjudicator's determination quashed for reasons including that there was an error of law on the face of the determination, albeit a non-jurisdictional error, relating to the incorrect interpretation by the adjudicator of the liquidated damages clause under the contract, which formed part of the reasons in the determination.

Decision

Emmett AJA, sitting as an additional Judge in the Technology and Construction List, agreed with Probuild, and held:

"Had the adjudicator not made the error of law in incorrectly interpreting the liquidated damages clause, he may have well allowed the claim by Probuild for liquidated damages such that the Adjudicated Amount should have been nil."2

Emmett AJA subsequently quashed the adjudication determination, and ordered the matter of the adjudication be remitted to the adjudicator for further consideration and determination according to law.

In coming to this decision, Emmett AJA considered three broad issues.

A court has jurisdiction to judicially review adjudication determinations

First, Emmett AJA examined whether a court had jurisdiction to judicially review an adjudicator's decision. After considering the powers of the Court under the Supreme Court Act 1970 (NSW) and the process of adjudication under Part 3 of the Building and Construction Industry Security of Payment Act 1999 (NSW), Emmett AJA found that a determination by an adjudicator is amendable to judicial review:

"Accordingly, in principle, a determination by an adjudicator is amendable to judicial review under s 69 of the Supreme Court Act and there is no reason why the Court would not have power to quash a determination by an adjudicator that involves an error of law." 3

Brodyn is only obiter for issues relating to judicial review for errors of law

Emmett AJA went on to analyse the decision of Hodgson JA in Brodyn Pty Ltd v Davenport. 4 Shade attempted to rely on the case as authority that "the scheme of the Security of Payment Act appeared strongly against the availability of judicial review on the basis of non-jurisdictional error of law"5 . However, his Honour did not agree, noting that the case had been thrown into doubt as a result of Kirk v Industrial Court of New South Wales6 and that Brodyn was not strictly binding on his Honour:

"Mason P and Giles JA agreed with Hodgson JA without comment. However, the correctness of certain propositions advanced by Hodgson JA [in Brodyn] have now been put substantially in doubt by the High Court. That is to say, legislation that would take away from the Supreme Court a power to grant relief on account of jurisdictional error is beyond the legislative power of the New South Wales Parliament. Further, while I would be very slow to depart from observations made by such a distinguished jurist as Hodgson JA, his Honour's observations are not strictly binding, quite apart from the doubt cast on his Honour's analysis by the High Court.
... the case is only authority for the proposition that a person who contracts to do work without a licence in contravention of s 4 of the Home Building Act 1989 (NSW) is not precluded from receiving progress payments under the Security of Payment Act. Hodgson JA held that there was in fact no error of law and, accordingly, the observations made by his Honour as to whether relief by way of judicial relief is available under s 69 of the Supreme Court Act were strictly obiter dicta and the question therefore remains open." 7

The Security of Payment Act does not exclude the courts' ability to judicially review an adjudicator's determination

Finally, Emmett AJA considered the language of sections 25 and 27 of the Security of Payment Act, and stated that there was nothing in the language or intention of the Act that operated to exclude the jurisdiction of the courts to undertake judicial review of an adjudicator's determination:8

"I do not consider that there is a clear indication or implication to be found in the Security of Payment Act that the jurisdiction conferred by s 69 of the Supreme Court Act is intended to be excluded ..."

Having identified an error of law made by the adjudicator (namely that Probuild was required to prove fault by Shade before being entitled to deduct liquidated damages), and that it was material, Emmett AJA quashed the determination.9

https://www.caselaw.nsw.gov.au/decisio n/575f4f9ce4b058596cb9c344

Footnotes

1 [2004] NSWCA 394; 61 NSWLR 421
2 At [79]
3 At [56]
4 [2004] NSWCA 394; 61 NSWLR 421
5 At [58]
6 [2010] HCA 1; 239 CLR 531
7 At [64], [65]
8 At [74]
9 At [78]–[80]

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Chambers Asia Pacific Awards 2016 Winner – Australia
Client Service Award
Employer of Choice for Gender Equality (WGEA)
See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More