New Wheeling Charges For Renewable And Efficient Cogeneration Power Projects In Mexico

FL
Foley & Lardner
Contributor
Foley & Lardner LLP looks beyond the law to focus on the constantly evolving demands facing our clients and their industries. With over 1,100 lawyers in 24 offices across the United States, Mexico, Europe and Asia, Foley approaches client service by first understanding our clients’ priorities, objectives and challenges. We work hard to understand our clients’ issues and forge long-term relationships with them to help achieve successful outcomes and solve their legal issues through practical business advice and cutting-edge legal insight. Our clients view us as trusted business advisors because we understand that great legal service is only valuable if it is relevant, practical and beneficial to their businesses.
The new wheeling charges are based on a resolution adopted by the CRE on May 28, 2020.
Mexico Energy and Natural Resources
To print this article, all you need is to be registered or login on Mondaq.com.

On June 10, 2020, the Federal Electricity Commission (Comisión Federal de Electricidad, known as CFE), the Mexican utility operator, published in the Official Gazette (Diario Oficial de la Federación) the new wheeling fees for renewable and efficient cogeneration power projects that  executed an interconnection agreement with CFE prior to the energy reform in 2013.

The new wheeling charges are based on a resolution adopted by the CRE on May 28, 2020. It is worth mentioning that neither the resolution nor the methodology for the calculation of the new wheeling charges has been published in the Official Gazette by the Energy Regulatory Commission (CRE). This means that CFE is implementing resolutions adopted by the CRE that have not been enacted and are not in effect yet.

The new wheeling charges are the following:


Voltage  Wheeling Charges
June 2020 (peso/kWh 
New Wheeling Charges
(peso/kWh) 
Impact 
High Voltage  0.05100  0.27857  446% 
Medium Voltage  0.05100  0.25865  407% 
Low Voltage  0.10199  0.89284  774% 

Affected parties, meaning all companies that have a power generation permit granted by the CRE under the self-supply or power cogeneration scheme and have executed an Interconnection Agreement with CFE (a CIL) under the Public Electricity Service Law (Ley del Servicio Público de Energía Eléctrica), and the off-takers of such permits, are entitled to challenge these new wheeling charges through an amparo procedure.

Considering that the new wheeling charges may take effect in July 2020, the amparo claim should be submitted within 15 business days of June 10, 2020.

Foley attorneys have the necessary experience in energy and administrative litigation matters to assist clients in challenging this new resolution and protecting their investments in Mexico. 

Originally published 11 June 2020

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

New Wheeling Charges For Renewable And Efficient Cogeneration Power Projects In Mexico

Mexico Energy and Natural Resources
Contributor
Foley & Lardner LLP looks beyond the law to focus on the constantly evolving demands facing our clients and their industries. With over 1,100 lawyers in 24 offices across the United States, Mexico, Europe and Asia, Foley approaches client service by first understanding our clients’ priorities, objectives and challenges. We work hard to understand our clients’ issues and forge long-term relationships with them to help achieve successful outcomes and solve their legal issues through practical business advice and cutting-edge legal insight. Our clients view us as trusted business advisors because we understand that great legal service is only valuable if it is relevant, practical and beneficial to their businesses.
See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More