This case demonstrates how Courts deal with the existence of two construction contracts and decide which one is binding.
Australia Real Estate and Construction
To print this article, all you need is to be registered or login on Mondaq.com.

Intro­duc­tion

In the recent deci­sion of Stepanos­ki v Aslan [2018] NSWSC 1160, the New South Wales Court of Appeal had to grap­ple with whether:

  1. the par­ties involved were bound by the first build­ing con­tract that they signed; or
  2. whether the sub­se­quent con­tract, which was signed by the par­ties lat­er and back­dat­ed to the date of the ear­li­er con­tract, replaced the first contract.

The facts

On 14 Octo­ber 2014, the plain­tiffs entered into a cost-plus build­ing con­tract (Cost-Plus Con­tract) with the defen­dant builder in respect of the con­struc­tion of two res­i­dences on land that was owned by the plaintiffs.

In short, a costs-plus con­tract is a con­tract where the builder is paid the actu­al cost of work under­tak­en plus a per­cent­age over and above those costs on account of mar­gin and pre­lim­i­nar­ies. These con­tracts can be used when the total amount payable to the builder can­not be rea­son­ably deter­mined at the time of enter­ing into the con­tract, or the scope of the work is unknown, and the own­er takes the risk of that cost.

Sub­se­quent­ly, the plain­tiffs and the defen­dant signed anoth­er build­ing con­tract, being a home build­ing con­tract for work over $5,000 (Lump Sum Con­tract) and back­dat­ed to the date at which the Cost-Plus Con­tract was signed by the parties.

Under a Lump Sum Con­tract, a sin­gle 'lump sum' price for all the works is agreed before the works are com­menced by the builder.

The plain­tiffs alleged breach­es of the build­ing con­tract by the defen­dant and com­menced pro­ceed­ings claim­ing damages.

In the course of the pro­ceed­ings, the Court was required to deter­mine the terms of the build­ing con­tract and, in rela­tion to that par­tic­u­lar issue, was asked by the par­ties to decide whether the Lump Sum Con­tract was intend­ed to replace the Cost-Plus Contract.

The defen­dant builder ini­tial­ly argued that the Lump Sum Con­tract was not intend­ed to replace the Cost Plus Con­tract to any extent and that it was, in effect, no more than a sham. He assert­ed that the Lump Sum Con­tract was brought into exis­tence sole­ly to enable the plain­tiffs to rep­re­sent to their bank (who were financ­ing the project) that they had a con­tract with a builder for a fixed sum, a require­ment spec­i­fied in a loan approval giv­en to the plain­tiffs by their bank.

In the course of oral address­es after all of the lay evi­dence had been com­plet­ed, the defen­dant builder's posi­tion changed.

In that regard, the defen­dant was grant­ed leave to amend his Response and Cross Claim to assert, among oth­er things, that in Jan­u­ary 2015, the par­ties signed the Lump Sum Con­tract which they dat­ed 14 Octo­ber 2014 for the sole pur­pose of pro­vid­ing the doc­u­ment to the plain­tiffs' bank to assist the plain­tiffs to obtain finance for the project, but:

  1. the par­ties oral­ly agreed that they would con­tin­ue to be bound by and apply the Costs Plus Con­tract; and
  2. the defen­dant builder had informed the first plain­tiff a num­ber of times, and the first plain­tiff had agreed, that the cost of the project would be greater than the amount stat­ed in the Lump Sum Contract.

Deci­sion

In deter­min­ing whether the par­ties were bound by the Cost-Plus Con­tract (which was signed by the par­ties first) or whether the Lump Sum Con­tract (which was signed lat­er but back­dat­ed to the date of the Cost-Plus Con­tract) pre­vailed, Emmett AJA found at [69] that despite minor incon­sis­ten­cies in the con­tem­po­ra­ne­ous mate­r­i­al, the major­i­ty of the doc­u­ments relat­ing to the project (which includ­ed the pro­posed build­ing doc­u­ments, such as archi­tec­tur­al draw­ings and a build­ing quote) point­ed to the par­ties' inten­tion as being bound by the Lump Sum Contract.

In reach­ing that con­clu­sion, his Hon­our found at [13] that it was not pos­si­ble to find any agree­ment that the Cost-Plus Con­tract was to remain bind­ing on any par­ty in any way and, despite the dis­sat­is­fac­tion of the defen­dant, the arrange­ments (as between the par­ties) were changed in a crit­i­cal respect by the sign­ing of the Lump Sum Contract.

Accord­ing­ly, his Hon­our decid­ed that the par­ties were bound by the Lump Sum Contract.

Lessons

This case demon­strates how the Courts deal with the exis­tence of two con­struc­tion con­tracts and decide which one ought to bind the parties.

In that regard, the deci­sion of Emmett AJA high­lights how, in deter­min­ing the terms of a build­ing con­tract, the Court will attach sig­nif­i­cant weight to the con­tem­po­ra­ne­ous mate­r­i­al rather than the oral evi­dence pre­sent­ed by at tri­al the parties.

The case also serves as a time­ly reminder to con­trac­tors that a sec­ond con­tract, entered into sole­ly for finance pur­pos­es can be found to be bind­ing, pro­vid­ed the par­ties act in a way which sug­gest the con­tract applies to them, as occurred in Stepanos­ki as detailed above.

For further information please contact:

Sean Greenwood, Associate
Phone: +61 2 9777 8315
Email: stg@swaab.com.au

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

You say toma­to, I say tom­ah­to: The bat­tle of forms and build­ing contracts

Australia Real Estate and Construction

Contributor

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More