Photovoltaic solar projects have become a rather conventional asset class. The technology is proven at scale, the revenue stream looks and feels like an annuity and, with customers like Walmart and your local utility, the sizzle is gone. In recent years, investors have flocked to the space hoping to seize on the final few opportunities for high-returns, coupled with infrastructure-like stability. As the market matured, margins compressed and double digit returns are now likely permanently in the past. Still looking for sizzle, investors, now comfortable with solar as a generating asset, are exploring ways to invest earlier in the development cycle. The increased risk ought to provide increased yields, so the thought goes.

Happy to oblige, developers have been offering up their development pipelines for sale. These pipelines promise attractive returns and the offerings are timely. With the federal Investment Tax Credit set to step down at the end of the year, projects must commence construction by December 31, 2019 in order to take advantage of the current 30% tax credit. Adding to the frenzy is a sense that we may be approaching market saturation for investment grade offtake. Projects with strong contracted revenue streams from investment grade rated counterparties are scarce, and offtake tenures, once a standard 20-25 years, continue to plummet. Given these circumstances, the market will continue to see increased investment in solar platforms and development pipelines.

The question inevitably arises whether the investment community understands solar development assets as well as it understands solar operating assets. If the glossy CIMs in circulation now are any indication, the answer is "no."

This is part one of a four part series exploring how to value and diligence a solar development pipeline. This series will consider commercial and industrial (C&I) and utility scale pipelines and will not address residential pipelines.

Beyond Bragawatts

Development pipeline and operating portfolios are measured in megawatts. Generally, investments in solar portfolios at NTP ("notice to proceed") or COD ("commercial operation date") are assumed to be de-risked. System sizes tend to decrease slightly from NTP to COD, but these changes typically do not go beyond post-closing quibbles over liquidated damages.

Development pipelines, on the other hand, are mixed bag of risk. Pipelines tend to include (in order of declining risk): early stage assets, later stage assets and "NTP ready" assets. Since attrition occurs as projects move from early stage to NTP ready, developers looking to sale their pipelines often provide their views on the pull-through rate for projects in their pipelines. A common way to think of a pull-through rate is in the context of the offtake agreement. The offtake agreement, often a Power Purchase Agreement (PPA), is the centerpiece of the solar project. Developers pour an enormous amount of sweat equity into acquiring offtake. Sales cycles for unsolicited PPAs last anywhere from 3 months to 3 years. Sophisticated offtakers hold competitive RFP processes that reward bidders that are willing to build projects below cost in the hope that they will be awarded follow-on business. With the exception of feed-in-tariffs directly with a utility, offtake agreements are bespoke products of painstaking negotiation. Rightfully, many developers consider the PPA to be their biggest value-add and the most critical element of a project's success.

Therefore, a potential investor may see pipelines broken down into PPA-related categories for the purposes of determining attrition. For instance, a common set of categories and pull-through rates would be as follows: Projects in the "proposal" stage have a 5% likelihood of success; projects in the "term sheet" stage have a 30% likelihood of success; projects in the "negotiation" stage have a 50% likelihood of success; and projects in the "executed PPA" stage have an 75% likelihood of success. This approach is elegant in its simplicity, while maintaining just enough number crunching for an analyst.

If you are thinking that it probably takes more than a few short clicks to get to the probability-weighted megawatt number of a development pipeline, you'd be right.

Every individual solar project has four pillars on which it succeeds:

Pillar I: Revenue Streams

Pillar II: Interconnection

Pillar III: Site Control

Pillar IV: Permitting

A fault in any of the four could represent a binary risk to a project. In order to value a pipeline, one must diligence each of the four pillars and be able to assign a stage of development to each project for each pillar. Complicating matters, within a single pipeline there is often a stunning lack of standardization across the project documents that govern the four pillars. Interconnection requirements vary by utility, down to the feeder. Permitting requirements vary by jurisdiction, down to the subdivision. And site control is, well, site specific.

This post will explore the first pillar of project success, Revenue Streams.

Pillar I: Revenue Streams

A. Structure and Authority

Within a single development pipeline, you may encounter the following types of offtake agreements:

  • Feed-in-Tariff (a project directly with a utility)
  • Net-metered PPA (a project sited on or off the offtaker's premises)
  • "Behind-the-meter" PPA (a project sited on the offtaker's premises)
  • Contract for Differences (a project sited remotely from the offtaker)
  • Community Solar Agreement (with subscription agreements)

Because each of these agreements rely on specific statutory authorities, legal review is essential. This post will not address the legal considerations of the terms and conditions of PPAs. Instead, we will focus on the nature of the offtake agreement and raise certain considerations for pipeline valuation. In brief:

  • Feed-in-Tariff: This agreement generally represents the least amount of risk. The offtaker is a utility that likely maintains an investment grade rating, the agreement is drafted by a sophisticated party and the agreement itself is sanctioned by the authority having jurisdiction. Therefore, early diligence questions may be limited to any deadlines associated with the commissioning of the system and ensuring that the project generally complies with the terms of the feed-in-tariff. Additionally, look out for hefty performance and payment assurance provisions that require substantial bonding, a letter of credit or cash collateral.
  • Net-Metered PPAs: This PPA is executed pursuant to a net metering tariff authorized by the state public utilities commission or public services commission and implemented by the utility. It is important here to ensure that the PPA and the project are structured in accordance with the applicable net metering tariff and all eligibility requirements are met including timely submission of application. Net metering tariffs vary by state and, in some cases, by the utility territory. Additionally, some states have multiple net metering tariffs. It is not unusual to find that an executed PPA may not fit within the confines of the net metering tariff that the developer intends to use. This increases regulatory risk and may require redevelopment, transforming a later stage asset to an early stage asset. It is particularly important to understand the applicable net metering rules related to system size, co-location of multiple systems, remoteness from the offtaker, and the eligibility of the offtaker itself.
  • Behind-the-Meter PPA: This is a bi-lateral agreement between the system owner and the offtaker for a system located on the offtaker's property. The primary diligence question here is whether behind-the-meter PPAs are enforceable in the jurisdiction where the system is set to reside. If so, these agreements can be the simplest to diligence. Generally, the offtaker also grants site control for the project, which also streamlines review. Risk for these projects may be particularly concentrated on the individual offtaker, as the single counterparty responsible for the revenue from and access to the system. What's more, because the system is generally sited on the offtaker's land or roof, in the event of termination or at the expiration of the PPA, alternative offtake opportunities may be limited.
  • Contract for Differences (CFD): This is used for projects sited remotely from the offtaker, but within the same utility or regional transmission organization (e.g. PJM) territory. The CFD provides a fixed-for-floating rate and the agreement may indicate that it is for the physical delivery of power at the node. It is important to consult with a legal expert when reviewing this contract to ensure compliance with Dodd-Frank and other applicable regulations.
  • Community Solar: This offtake arrangement (often a form of net metering) is enjoying popularity at the moment. "Community solar" is used to designate a wide variety of project configurations in the development community. If often means a structure whereby the system owner sells electricity to the utility, provided that the system owner is able to amass a certain amount of subscribers within the utility's territory. Compliance with the precise statutory authority and the utility's guidance is critical here. Early diligence should reveal the number of subscriptions and the total megawatts subscribed, as well as the number of subscriptions and total megawatts required to be subscribed in order to commence construction and to achieve commercial operation. Additionally note that there may be quota limitations with regard to certain classes of subscribers.

B. PPA Tenure and Price

Twenty years was the gold standard in solar. Recently, as the cost to deploy solar has fallen, so too have PPA tenures. Today, ten year tenures are not unusual. Conversely, the useful life of photovoltaic systems continues to lengthen and the degradation of the panels themselves is lessening. Thus, in order to recognize the true value of the system (and to stay competitive), investors are assigning value to the "tail period" after the expiration of the PPA. Some considerations for tail period valuation include:

Questions Related to Potential or Additional Offtake –

  • Where is the system located?
    • Is it on the offtaker's property?
    • Is it on a building or near a population center where continued occupancy is expected?
    • How long are the roof warranties valid?
  • How long does the site control last?
    • Does the system have the right to be on the land post-PPA? For how long?
    • What are the renewal terms?
    • How competitive is the lease rate?
  • What alternative offtake arrangements could be made given the regulatory landscape?

Questions Related to Individual Investor Risk Appetite –

  • Where else / for what other investments / under what circumstances does the investor take merchant risk?
  • Is there a hedge or insurance product to meet any floor return requirements?

Along with tenures, PPA prices continue to fall. It is important to understand each of the various revenue streams of a project individually to appreciate the significance of the portion flowing from the PPA. In certain areas with high market rates for solar renewable energy credits (SRECs), it is not unusual for PPA rates to be at $0.02/kWh or lower. It is important to understand your risk appetite and desired balance of contracted PPA revenue and market-based incentive revenue.

C. Offtakers

Most investors know to diligence the creditworthiness of the offtaker in order to determine a default rate. In recent years, many investment grade rated offtakers have made significant renewable procurements (as seen in splashy PR campaigns and Super Bowl ads). There is growing concern that investment grade rated offtake is no longer readily available in the market. Therefore, many investors are now investing in projects with unrated offtakers or offtakers with below investment grade credit. Shadow ratings are gaining acceptance. Another important consideration is PPA price. If the PPA rate is lower than the avoided cost of energy, a default is less likely. If, on the other hand, the developer were to be so lucky as to have executed a PPA with a rate above the avoided cost of energy (maybe even with an escalator), it is important to consider the possibility an economic default. Finally, if a default is a genuine concern, attention should be paid to the location of the system and possible alternative offtake arrangements.

D. Environmental Incentives

Projects that rely heavily on SRECs or other incentives present their own set of diligence considerations. If the incentives, like SRECs, are based on production, the yield of the system is critical. Therefore, it is important to check the developer's yield assumptions, if provided. Engaging an engineer to review the early energy models for larger projects is most prudent. Another consideration is that the value of tradable incentive, like SRECs, fluctuates over time. Thus, the value of the asset changes over time. This could be a critical consideration for an asset in early stage development that relies heavily on SRECs for its economics, particularly in a state where the renewable portfolio standard (RPS) is set to decline. Such fluctuations in value could mean that an otherwise normal development delay of 6 to 9 months poses a binary threat to the economics of the project. Finally, if the incentive is grant-based, it is important to understand, at least in broad strokes, how the grant is awarded and recognized, which may affect the tax and accounting treatment of a project.

E. Stages of Development

Given the diverse array of offtake varieties, it is not surprising that there is no industry standard for stages of development related to a PPA. Therefore, when considering acquisition of a pipeline or platform, it is important to understand how the developer categorizes its own development stages. Additionally, investors ought to consider their own monetization strategy for the assets in the pipeline in order to determine the relative importance of the offtake. For instance, is the investor intending to build, own and operate the assets? Is the investors looking to sell the assets at COD? Or, is there a strategy to obtain large amounts of megawatts for a different type of exit? If you have the answer to these questions during the diligence process, the relative value of the stages of development for the PPA may emerge much more clearly.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
 
In association with
Related Topics
 
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Mondaq Free Registration
Gain access to Mondaq global archive of over 375,000 articles covering 200 countries with a personalised News Alert and automatic login on this device.
Mondaq News Alert (some suggested topics and region)
Select Topics
Registration (please scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions