Extensions Of Time And Loss And Expense

WB
Wedlake Bell

Contributor

Wedlake Bell logo
We are a contemporary London law firm, rooted in tradition with a lasting legacy of client service. Founded in 1780, we recognise the long-standing relationships we have with our clients and how they have helped shape our past and provide a platform for our future. With 76 partners supported by over 300 lawyers and support staff, we operate on a four practice group model: private client, business services, real estate and dispute resolution. Our driving force is to empower our clients by providing quality legal advice, insight and intelligence that enables them to achieve their goals whether personal or business. We are large enough to advise on the most complex matters, but small enough to ensure that our people and our work remain exceptional and dynamic. Building relationships is at the heart of everything we do.
In this important decision (one of several to be decided between these parties) the court clarified the position in respect of several issues which arise regularly on construction projects.
United Kingdom Litigation, Mediation & Arbitration

Walter Lilly & Company Limited v Mackay & Anor [2012] EWHC 1773 (TCC)

In this important decision (one of several to be decided between these parties) the court clarified the position in respect of several issues which arise regularly on construction projects. In relation to loss and expense claims, the judge confirmed that the obligation on the Architect/Contract Administrator to "ascertain" loss and expense does not mean that the contractor has to prove its claim "beyond reasonable doubt" instead, the balance of probabilities test applies.

The judge also confirmed that it is legitimate for the contractor to bear in mind the knowledge that the Architect/Contract Administrator has of the project when supplying supporting documents for his claim. The judge also took the opportunity to clarify the position with regards to extensions of time where there are concurrent delays to the works. It was confirmed that (unless there are express contractual terms stating otherwise) where there are two concurrent delays, one which entitles the contractor to an extension of time and one which does not, then there should not be any apportionment between the two delays. The contractor should receive an extension of time for the whole period of the relevant delay.