Switzerland: The 2012 ICC Arbitration Rules

On 1 January 2012, the revised ICC Arbitration Rules entered into force. They contain new and amended provisions promoting the efficiency of the arbitral process and dealing with the increased complexity of commercial relationships. The new emergency arbitrator proceedings also allow the parties to obtain urgent interim relief prior to the constitution of the arbitral tribunal.

1. BACKGROUND AND MAIN PURPOSE OF REVISION

Following a more than two-year revision process, the revised arbitration rules of the International Chamber of Commerce (ICC) entered into force on 1 January 2012 (the "Rules"). The Rules apply to all arbitrations commenced on or after 1 January 2012, irrespective of the date of the arbitration agreement.

The revision process was led by a task force which gathered input from members of the ICC and arbitration practitioners. The task force also included users of ICC arbitration. Based on a consensus that the previous 1998 ICC Rules worked well in principle and needed to be updated only in areas which had either evolved or had presented certain difficulties in practice, the main aims of the revision were to codify established practices of the ICC, to take into account the increasing number of so-called "complex arbitrations" involving multiple parties and/or multiple contracts, to consider certain trends in international arbitration and, particularly, to address the arbitration community's growing concern that there was at times a disproportion between the issues at stake and the time and cost of the arbitration procedure.

2. SAVING TIME AND COST

2.1 Introduction

The main amendments designed to increase time and cost efficiency of the arbitral process are reflected in the new Articles 22 and 24 of the Rules.

2.2 Effective Case Management

Article 22(1) imposes on the arbitrators and the parties the duty to conduct the arbitration in an expeditious and costeffective manner, having regard to the complexity and value of the dispute. The duty of the arbitrators to effectively manage the case is an ongoing task which continues throughout the proceedings and will encourage the arbitral tribunal to become familiar with the facts and issues of the case from the very start and actively manage the arbitration to ensure that is conducted efficiently. The parties' conduct in this respect is one factor under the Rules to be taken into account by the arbitral tribunal when deciding on the allocation of the costs of the arbitration. This gives the parties an incentive to refrain from dilatory tactics.

«The revised ICC Rules promote efficiency of the arbital process.» 2.3 Case Management Conference

Article 24(1) introduces a mandatory obligation for the arbitral tribunal to conduct a case management conference. Such conference is an effective means towards promoting time and cost efficient proceedings. It is to be held in the initial stages of the proceedings, either when drawing up the Terms of Reference or "as soon as possible thereafter". A case management conference does not require a meeting in person - rather, modern means of communication can be used.

The arbitral tribunal can request the attendance of the "parties in person or through an internal representative" at the case management conference (Article 24(4)). The presence of a party representative guarantees that the decisions taken with regard to the proceedings are backed by the parties themselves rather than only their counsel. Also, it may assist in finding an agreement on procedural means which are time and cost efficient, but entail certain procedural risks (such as the decision to have limited document disclosure and production) whilst ensuring that the parties fully understand such risks.

2.4 Case Management Techniques

The main purpose of the case management conference is to discuss procedural measures which will help control time and costs of the proceedings. To assist the arbitral tribunal and the parties, the drafters of the Rules have identified in a new Appendix IV a non-exhaustive list of the most common case management techniques. Such techniques include bifurcation of the procedure (that is, dividing the proceedings into several stages), identification of issues which can be decided on the basis of documents only, certain basic rules regarding the production of documentary evidence, and indication of issues on which the parties shall focus during the hearing.

3. DEALING WITH COMPLEX ARBITRATIONS

3.1 Introduction

Commercial relationships increasingly lead to complex arbitrations involving multiple parties and/or multiple contracts. The new provisions in Articles 6 to 10 of the Rules mostly reflect the current practice of the International Court of Arbitration of the ICC (the "Court") and the Secretariat of the Court (the "Secretariat"), although the revision also introduces some changes.

It is important for users to note that the new Articles 7 to 10, as well as Article 6(4) which deals with the jurisdictional aspects of complex arbitrations, do not entail a diminishment of party autonomy or a dilution of privity of the arbitration agreement. Parties can still rely on the fact that, from the viewpoint of the Rules, an arbitration agreement is binding upon the parties to that particular arbitration agreement only, unless the Court deems that the parties "may have agreed" to arbitrate their claims falling under more than one arbitration agreement together in one arbitration.

«The Rules contain new comprehensive provisions for complex arbitrations.» 3.2 Joinder of Additional Parties

Article 7 deals with the joinder of additional parties after the commencement of an arbitration. It follows from Article 6(4) that joinder can arise under two basic scenarios. First, where the additional party is a party to the same arbitration agreement forming the basis for the arbitration between the original parties, and, second, where the additional party and the original party wishing to join the additional party are bound by another arbitration agreement.

Without the consent of all parties, joinder is only possible prior to the confirmation or appointment of any arbitrator. In other words, a constituted ICC arbitral tribunal is not entitled to join a third party unless all parties agree.

3.3 Claims between Multiples Parties

Article 8 of the Rules codifies the Court's current practice regarding claims between multiple parties. Also in this case, it follows from Article 6(4) that such claims can be made under the same or under different arbitration agreements. They may also be made under a single arbitration agreement entered into between all of the parties to the multi-party arbitration, or under a different arbitration agreement entered into between only some of the parties to the multi-party arbitration.

Article 8 permits the making of additional claims until the signing of the Terms of Reference. Upon signature of the Terms of Reference pursuant to Article 23 of the Rules, the general rule for new claims under Article 23(4) will apply.

3.4 Multiple Contracts

Article 9 addresses the issue of multiple contracts. This issue can arise both in the context of an arbitration between two parties or in a multi-party situation. Parties who have entered into multiple contracts may have provided for a framework arbitration agreement to govern all disputes arising out of the multiple contracts entered into between the parties. However, framework arbitration agreements are not very frequent in practice. Thus the multiple contracts provision in Article 9 – albeit mentioning both alternatives – deals primarily with a situation in which there are multiple arbitration agreements under the Rules.

3.5 Consolidation

Article 10 concerns consolidation of arbitral proceedings and replaces Article 4(6) of the 1998 ICC Rules. Pursuant to Article 10, it is the Court, and not the arbitral tribunal, which decides issues of consolidation.

This provision has undergone important changes and the possibilities of consolidation have been broadened. Consolidation is now possible in three basic scenarios, namely (1) if all parties agree to consolidation; (2) if all claims made in the arbitrations fall under the same arbitration agreement; and (3) where the claims in the arbitration are made under different arbitration agreements, however in this last case only if (a) the consolidation involves arbitrations between the same parties; (b) the disputes in the arbitrations concern the same legal relationship; and (c) the arbitration agreements are compatible. It bears emphasizing that the Court may, but is not obliged to order consolidation if these conditions are met.

In principle, an application for consolidation can be made at any stage while the arbitrations are pending under the Rules. That being said, the Court will take into account all relevant circumstances when deciding whether to order consolidation, particularly how far each of the arbitrations is advanced, whether any arbitrators have been confirmed or appointed and, if so, whether the same persons shall act as arbitrators in the consolidated arbitration.

4. THE NEW GATEKEEPER TEST OF ARTICLE 6

Article 6 contains one of the most significant changes to the 1998 ICC Rules. Under Article 6(2) of those rules, if the respondent did not file an answer to the request for arbitration or if objections regarding the existence, validity or scope of the arbitration agreement were raised, the matter had to be referred to the Court for a prima facie decision on jurisdiction.

Statistics showed, however, that only a very small percentage of cases submitted to the Court failed to meet the prima facie test. Therefore, it was decided that, under the revised Rules, the Secretary General of the ICC Court should function as a "gatekeeper" and decide which cases should be submitted to the Court and which cases should go directly to the arbitral tribunal. In other words, the new general rule is that the arbitral tribunal itself will be the first body to decide on jurisdictional issues. The Court will decide jurisdictional issues only in the exceptional case that the Secretary General decides to submit such questions to the Court. This new regime is expected to considerably further the efficiency of ICC arbitration, particularly with respect to the constitution of the arbitral tribunal.

The other important change regarding the prima facie test concerns cases in which there are multiple parties and/or multiple arbitration agreements (Articles 7 and 9). While the 1998 ICC Rules do not contain specific rules as to how such cases are dealt with, Article 6(4) of the revised Rules describes the tests that the Court will apply in these particular situations. The main purpose of this clarification is to provide transparency.

5. EMERGENCY ARBITRATOR

The provisions on emergency relief are entirely new to ICC arbitration. Article 29 of the Rules is the core provision that sets the framework for the new regime for urgent interim or conservatory measures which cannot await the constitution of an arbitral tribunal under the Rules (defined as "Emergency Measures"). The detailed procedural rules for the emergency arbitrator proceedings are determined in Appendix V.

«Emergency arbitrator proceedings enable urgent relief before the tribunal is constituted.» The main reason for introducing emergency arbitrator proceedings was to fill the vacuum before the constitution of the arbitral tribunal. During this time, which can last up to several months, if one of the parties needs urgent interim relief under the 1998 ICC Rules, it usually has no option other than to address a state court. While in many cases this is an efficient and appropriate course of action, there are situations in which such action is not possible or not appropriate. In such circumstances, the parties to an ICC arbitration agreement can now obtain Emergency Measures from an emergency arbitrator within approximately 15 days.

In order to make it abundantly clear that the emergency arbitrator procedure shall be an additional option and not curtail a party's ability to seize a state court, Article 29(7) stipulates that, from the viewpoint of the Rules, any party can address any competent judicial authority notwithstanding the applicability of the emergency arbitrator proceedings.

The emergency arbitrator is available whenever parties have agreed to arbitrate their dispute under the Rules, provided, however, that the arbitration agreement was concluded on or after 1 January 2012. In other words, the emergency arbitrator rules to not apply retroactively. If parties do not wish to be bound by these rules, they must explicitly exclude them. The Rules provide for an additional standard arbitration clause explicitly excluding the applicability of the emergency arbitrator. Whilst such exclusion is not generally advisable, there may be circumstances in which it is warranted.

It is important to note that the new emergency arbitrator rules apply only to "parties that are either signatories of the arbitration agreement" or "successors to such signatories". This limitation means that so-called extension theories, which are sometimes applied in order to draw non-signatories into arbitration, cannot be relied upon in emergency arbitrator proceedings. Moreover, it excludes the application of the emergency arbitrator rules to treaty-based arbi- trations, which is particularly relevant with respect to investor/state disputes.

The emergency arbitrator's decision (defined as the "Order") is binding upon the Parties and the Parties expressly undertake to comply with the Order. By contrast, it is not binding on the arbitral tribunal, which may modify, terminate or annul the Order once it is constituted.

6. OUTLOOK

The 2012 ICC Rules set a new standard for institutional arbitration rules that will be welcomed by the arbitration community. Whilst maintaining the typical features of ICC arbitration, the Rules face up to the increasing challenges of modern-day arbitration and will meet the needs of the users of ICC arbitration.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

More Popular Related Articles on Litigation, Mediation & Arbitration from Europe
Those of you who are familiar now with the portal process may know the answer to the question – does responding to a settlement offer one day after the 15 working day time frame mean the offer is withdrawn or does it still stand?
A discussion on a recent case, where the High Court departed from the normal costs rules that follow an offer to settle intended to have the costs consequences associated with Part 36 of the Civil Procedure Rules.
Some important changes to costs in legal proceedings take effect from 1 April 2013. One such change affects the operation of Conditional Fee Agreements (CFAs).
London as a seat of arbitration, and English law as a law governing contracts, are probably the most popular options for trans-border dispute resolution clauses in transactions involving Ukrainian business.
Hkruk II (CHC) Limited v Marcus Alexander Heaney [2010] EWHC 2245 (Ch) is about a land owner who obtains an injunction against a developer to protect his rights to light.
The Courts of Justice Law 1960 gives the courts in Cyprus discretion to issue a wide variety of provisional measures.
Care home providers are often at the mercy of local authorities as to price and price review for residential care.
The past two decades have seen an increase in trade globalization and growth of transnational companies, resulting in an escalation of cross-border disputes.
 
Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert
Email Address
Company Name
Password
Confirm Password
Mondaq Topics -- Select your Interests
Accounting and Audit
Anti-trust/Competition Law
Consumer Protection
Corporate/Commercial Law
Criminal Law
Employment and HR
Energy and Natural Resources
Environment
Family and Matrimonial
Finance and Banking
Food, Drugs, Healthcare, Life Sciences
Government, Public Sector
Immigration
Insolvency/Bankruptcy, Re-structuring
Insurance
Intellectual Property
International Law
Litigation, Mediation & Arbitration
Media, Telecoms, IT, Entertainment
Privacy
Real Estate and Construction
Strategy
Tax
Transport
Wealth Management
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.