This month the 9th Circuit upheld the Fish and Wildlife
Service's biological opinions finding that a proposed silver
and copper mine in northwestern Montana would not result in
"adverse modification" to critical habitat of the bull
trout or "jeopardy" to the grizzly bear, both of which
are federally listed as threatened species.
Rock Creek Alliance, an environmental plaintiff, had challenged
the two biological opinions, alleging that the FWS had violated the
Endangered Species Act and acted arbitrarily and capriciously in
making the "no jeopardy" and "no adverse
modification" findings. The district court upheld the
FWS's determinations, and Rock Creek Alliance appealed raising
four alleged defects. In a brief opinion that gave "deference
due to the agency," the court rejected each of the four
claims.
Use of Large-Scale Analysis
To determine the mine's impact on critical habitat for the
bull trout, FWS conducted a "large-scale analysis" in
which it compared the relatively small area of affected critical
habitat to the total area of critical habitat. Rock Creek Alliance
argued that this was improper. But the court upheld FWS's
approach because it did not focus solely on the scale of the
impact, but also on other features such as duration of the impact
and effects on the habitat's functionality. FWS acted
reasonably because it did not use large-scale analysis in an
"attempt to hide the local impacts of the action."
Failure to Consider Recovery in a Separate Section of
Biological Opinion
Rock Creek Alliance argued that FWS failed to adequately analyze
the mine's impact on bull trout recovery. The court disagreed.
Even though FWS did not address recovery in a "separate,
distinct section" of the biological opinion, as contemplated
by an FWS guidance memorandum, it did explicitly address the issue
of recovery elsewhere. Thus, giving a fair reading to the
biological opinion and appropriate deference to the agency, the
court found that FWS had adequately considered bull trout
recovery.
Improper Method of Calculating Mitigation Habitat
Rock Creek Alliance alleged that in calculating mitigation
habitat requirements for the grizzly bear, FWS failed to account
for the effect of existing development on proposed mitigation
habitat. The court disagreed, noting that FWS had expressly
acknowledged the effects of existing development on mitigation
habitat. In addition, the court found that FWS was not required to
replace affected habitat on an acre-for-acre for basis. More
importantly, the court found that the mitigation plan was "
multi-faceted," including activities beyond Revett's
required acquisition of mitigation land parcels, and that
"collectively, the measures would reduce, remove or more than
offset the potential adverse effects of the proposed
action."
Speculative Habitat Mitigation Plan
Rock Creek Alliance argued that the grizzly bear habitat
mitigation plan was unreasonably speculative. The court rejected
this argument, noting that the mine could not open until it had
satisfied mitigation requirements, that the mine had already
purchased 273 acres of mitigation land, and that the mine was
required to post a bond or a establish a trust fund to ensure its
compliance. Thus, FWS had satisfied the requirement of having
"binding and specific plans," "solid
guarantees," and a "clear, definite commitment of
resources.
The content of this article is intended to provide a general
guide to the subject matter. Specialist advice should be sought
about your specific circumstances.
Specific Questions relating to this article should be addressed directly to the author.
At the request of the US Department of Energy, Office of Fossil Energy, a NERA team led by Senior Vice President Dr. W. David Montgomery and Senior Consultant Dr. Sugandha Tuladhar has conducted an objective and independent study to assess the potential macroeconomic impacts on the US economy of liquefied natural gas (LNG) exports.
IRS Notice 2013-29 provides two methods for taxpayers to establish that construction of a qualified facility has begun, either by starting physical work of a significant nature or satisfying a safe harbor.
Investment worldwide in the first quarter of 2013 was $40.6bn, down 22% on a year earlier, due to a downturn in large wind and solar project financings.
Natural gas producers and landowners alike breathed a sigh of relief on April 24, 2013 as the Pennsylvania Supreme Court (the "Supreme Court" or "Court") overturned a lower court decision that questioned whether subsurface ownership rights of natural gas in shale formations should be treated differently than ownership rights of natural gas in conventional formations.
The Supreme Court of Pennsylvania issued a long-awaited decision yesterday in Butler v. Powers Estate, reversing a controversial superior court decision from September 2011.
As discussed previously on the blog, the IRS released Notice 2013-29 on April 15 which provided guidance on determining when construction has begun on a qualified renewable energy facility for purposes of the production tax credit.
A U.S. District Judge has denied a motion for summary judgment filed by oil and gas producer defendants, thus, enforcing the notion that an oil and gas producer can commit a trespass by engaging in hydraulic fracturing.