European Union: Examining The Impact Of Brexit On Public Procurement And Public Contracts

Last Updated: 14 June 2019
Article by David Hansom

The UK's proposed withdrawal from the institutions of the EU has now been 'flexibly' delayed up until 31 October 2019. Talks continue between the UK government and other political parties to try to find a compromise on a withdrawal agreement and future UK-EU relations. This article considers the impact of Brexit on public procurement and public contracts.

What impact does Brexit have on the key EU derived domestic regulations implementing the public procurement rules in the UK?

Public procurement regulation is devolved such that there are differing rules for Scotland from England, Wales and Northern Ireland. The impact on public procurement will depend on the type of Brexit which occurs. A Brexit which sees the UK, for example, joining the European Economic Area or the European Free Trade Association would likely see the UK be required to comply with existing and future EU legislation in the field of public procurement.

In the short term, the UK government has confirmed 'business as usual' in relation to public procurement. If the UK's withdrawal from the EU is cancelled or delayed, the current regime will of course continue to apply. If the UK leaves the EU under some form of managed withdrawal agreement, such an agreement will contain provisions dealing with public procurement. The current draft (Agreement on the withdrawal of the United Kingdom of Great Britain and Northern Ireland from the European Union (at Title VIII)) confirms that the existing EU rules will apply until the end of any transition period, and to any procurement process started during the transition period.

In the event of a so-called 'hard' Brexit, where the UK leaves all of the institutions of the EU without a managed withdrawal agreement, the UK has put in place amendment regulations which seek to ensure continuity of the existing legislative framework. The impact of these amendment regulations is set out below.

What is the key Brexit-related legislation impacting the procurement regime and what practical changes (if any) does it introduce? Is anything missing?

The key Brexit-related procurement legislation includes:

  • Public Procurement (Amendment etc) (EU Exit) Regulations 2019, SI 2019/560
  • Public Procurement (Amendment etc) (EU Exit) (No 2) Regulations 2019, SI 2019/623
  • Public Procurement etc (Scotland) (Amendment) (EU Exit) Regulations 2019, SSI 2019/112
  • Public Procurement etc (Scotland) (Amendment) (EU Exit) Amendment Regulations 2019, SSI 2019/114
  • Defence and Security Public Contracts (Amendment) (EU Exit) Regulations 2019, SI 2019/697
  • UK Statistics (Amendment etc) (EU Exit) Regulations 2019, SI 2019/489

The amendment regulations seek to ensure certainty in the event of a 'hard' Brexit. The key operative provisions in SI 2019/560 and SI 2019/623 are to:

  • replace references in the Public Contracts Regulations 2015, SI 2015/102 (PCR 2015) to the Official Journal of the European Union (OJEU) publication to a new UK e-portal system—a trial of the system is currently underway
  • removal of references to the EU from PCR 2015
  • the right for the relevant Secretary of State to set procurement thresholds
  • a new provision to entitle the UK to withhold information which it considers contrary to the essential interests of its security in public procurement activity
  • 18 months after the exit day, further provisions would amend the regulations further in respect of:
    • conditions relating to the government Procurement Agreement
    • life-cycle costing
    • duties owed to economic operators from certain other states

What is the government plan for implementation of procurement legislation on e-signatures in light of Brexit?

PCR 2015, reg 22 deals with electronic signatures. Contracting authorities must allow electronic submission of tenders and requests to participate, including encryption and time-stamping. There are provisions which relate to advanced electronic signatures where higher levels of trust and validation are required in PCR 2015, reg 22(17)(c).

The amendment regulations make specific provision that a UK government minister may make new exceptions or change existing exceptions to the obligation to undertake electronic procurement, because of technological developments. The UK government has stated that it is committed to modernisation of public procurement techniques and the opportunities afforded, for example, by blockchain technology.

What are UK-wide common legislative frameworks and how do they relate to/impact UK public procurement law post-Brexit?

'Common legislative frameworks' are common frameworks between the government of the UK and each of the UK's devolved administrations. These frameworks seek to establish a common policy in matters which are currently governed by EU law, but which are devolved to each administration—this includes public procurement law.

For this reason, mirroring provisions to the 'no deal' EU Exit regulations have been put in place for Scotland. The UK government has recently (4 April 2019) published a revised assessment of all of the different areas of EU law that apply to or are affected by the competence of the devolved administrations—this work is continuing.

If the deal is approved—what are the specific provisions for public procurement under the transitional arrangements in the Withdrawal Agreement?

The specific provisions set out in the current draft Withdrawal Agreement on public procurement are set out in Title VIII of the current draft (Agreement on the withdrawal of the United Kingdom of Great Britain and Northern Ireland from the European Union and the European Atomic Energy Community) dated 25 November 2018. This provides that the existing rules will apply to:

  • procurement procedures launched (as defined in the Withdrawal Agreement) by contracting authorities of the UK under those rules before the end of the transition period and not finalised (as defined in the Withdrawal Agreement) on the last day of the transition period
  • framework agreements or dynamic purchasing systems (DPS) set up either before the withdrawal date or during the transition period, and any call off contracts awarded under any such frameworks or DPS arrangements

If the deal is approved—what does the implementation of the Withdrawal Agreement mean for the commencement above legislation?

If a Withdrawal Agreement based on the 25 November 2018 version is implemented, SI 2019/560 and other secondary legislation will not come into effect until at least the end of any transition period. It is possible that the changes will not come into force at all depending on policy decisions reached between the EU and the UK.

If no deal—no deal remains the legal default position, what are the key differences contracting authorities must be prepared for on exit day? Are there any grey areas?

In the event of a so-called 'hard Brexit', the Amendment Regulations will apply on exit day.

The main practical change will be that contract notices and other notices will not be sent to the OJEU.

The UK government has intimated that it is keen to maintain access to public procurement markets across the EU for UK contractors and that EU contractors should be able to continue to access UK opportunities. It is currently not clear what the UK government would choose in terms of a new public procurement regime. Possible options include:

  • maintain the current regime. This has the advantage of being known and understood by UK contracting authorities and contractors and would involve minimal change and disruption to public sector supply chains in the short term. It is also possible, depending on the terms of any exit, that the EU seeks to require the UK to maintain the existing regime as a transitional step until new arrangements are agreed or as a requirement of any future co-operation arrangement. The EU has required compliance from other non-EU Member States in relation to procurement, for example in the Ukraine/EU collaboration agreement
  • amend the rules to simplify and seek to speed up procurement. This could involve merging the different rules for public contracts, concessions and utilities into one set of rules, freeing up use of the negotiated procedure still further and removing some of the more onerous procedural obligations on contracting authorities

A 'no deal' Brexit would create a range of potential uncertainties in relation to public procurement, including the jurisdiction of the Court of Justice in procurement disputes.

How will the UK's accession to the World Trade Organization Government Procurement Agreement impact UK public procurement in practice?

The World Trade Organization (WTO) Government Procurement Agreement (GPA) is a 'plurilateral' agreement, which means it is voluntary for WTO members to accede to it. It is formed of two sections, being the GPA (which sets out the obligations to open up public procurement markets and to ensure base levels of transparency) and the Coverage Schedules which set out the parties' market access commitments. The GPA will only apply to the relevant parts of the member's economy listed in the country's schedules.

There is unlikely to be significant immediate impact from the UK's accession to the GPA. The EU is a member of the GPA and all Member States take advantage of it via their EU membership. The EU public procurement rules embody many of the principles of the WTO GPA but develop these rules in many areas. It is possible that, in due course, the UK makes a policy decision to reform its public procurement rules to align these further with the WTO GPA as part of an overall simplification programme.

How will Brexit impact procurement disputes and the relevance of EU procurement case law in the UK?

There are detailed remedies rules in all of the public procurement directives and their corresponding regulations in the UK. These remedies rules have been developed by extensive case law from both the EU and the UK courts.

In the event of a managed withdrawal, the current rules would apply until the end of any transition period. In the event of a 'no deal' Brexit, there are a range of potential outcomes, but the starting position is that the EU case law would be persuasive on the UK courts and the Court of Justice would cease to maintain its jurisdiction over the UK. In practice, it may be that the EU would require jurisdiction of the Court of Justice in relation to previous procurement processes started or completed before the exit day. There is a very wide range of potential impacts of a no deal Brexit, from enforceability of overseas judgments through to the jurisdiction of the European courts, which would need to be addressed.

How does Brexit impact the drafting of public contracts? What guidance is available for contracting authorities drafting contracts for tender eg using the Model Services Contract as a guide?

Many contracting authorities (and suppliers) are making changes to their template public contracts in light of Brexit uncertainty. These changes are being made to tender documents –for example, to confirm that the procurement will continue regardless of the Brexit negotiations—as well as template contract terms and conditions. These changes include provisions to manage the risk of adverse changes in law affecting delivery of the contract, carving out Brexit as a force majeure event or seeking to limit the contractor's ability to increase prices due to Brexit. There is no 'one size fits all' for such provisions and each should be assessed on a case by case basis.

What can lawyers and contracting authorities do to prepare? Is Brexit delaying procurement planning and contract award decisions?

Brexit-related uncertainty in the sphere of public procurement does not appear to be affecting procurement processes in the UK, aside from a general reduction in public spending which has been seen in recent years. As Brexit draws closer, it is possible that public bodies delay significant procurement decisions until after the exit date to ensure legal certainty and the possibility of two different regulatory regimes applying to their procurements.

What guidance is available from the UK government and the European Commission for contracting authorities preparing for Brexit?

There is a wide range of information available from both the UK and EU in relation to Brexit preparedness and considerable commentary available on the impact on public procurement.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Similar Articles
Relevancy Powered by MondaqAI
Shepherd and Wedderburn LLP
 
In association with
Related Topics
 
Similar Articles
Relevancy Powered by MondaqAI
Shepherd and Wedderburn LLP
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Mondaq Free Registration
Gain access to Mondaq global archive of over 375,000 articles covering 200 countries with a personalised News Alert and automatic login on this device.
Mondaq News Alert (some suggested topics and region)
Select Topics
Registration (please scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions