Keywords: employer's challenges, adjudicator's award, penalty clauses

1. Court Demolishes Employer's Challenges to Adjudicator's Award

Seventeen years after the Construction Act went live, the ground rules of adjudication are still being tested. In Wycombe v. Topevent the employer challenged enforcement of an adjudicator's decision, claiming that there was more than one dispute and that there were breaches of natural justice, because the adjudicator did not have a site visit or meeting and did not decide the dispute on the basis of the parties' submissions. In dismissing the challenges, Mr. Justice Coulson restated some key principles of adjudication.

He decided that a demolition contractor's claim for the costs of an allegedly wrongful termination and its overall claim for all outstanding sums were not separate disputes. There was a clear and obvious link between them. Even if they were separate disputes, under the applicable TecSA rules the parties could agree to include further matters in the adjudication and the employer had acquiesced in, and not objected to, the adjudicator dealing with both claims.

The adjudicator did not have to have a site visit or meeting. Organisation of an adjudication, the procedure and the steps required before the decision is issued, are all matters uniquely for the adjudicator. It is up to them to decide what they need in order to reach their decision.

The judge also ruled that the adjudicator's valuation decision had been based on both parties' submissions. More widely, the judge said that an adjudicator has to do their best with the material provided and has considerable latitude to reach their own conclusions based on that material. In his view, that latitude is inevitably even wider, now that the original Construction Act requirement of a written contract has gone. An adjudicator's conclusion about the nature and terms of the contract could affect their approach to valuation issues. What an adjudicator cannot do, however, and certainly not without warning the parties in advance of the decision, is to make good deficiencies in the claiming party's case or to plug what they see as a gap in that case, by having regard to something they have been told to ignore.

Wycombe Demolition Ltd v. Topevent Ltd [2015] EWHC 2692

2. Challenging Jurisdiction But Paying the Adjudicator – Not Waiving But...?

A defendant in adjudication proceedings challenged the adjudicator's jurisdiction and fully reserved its rights. It also paid the adjudicator's fees, without any covering letter or explanation, but did that payment sink its challenges to jurisdiction?

The adjudicator's terms had not been expressly accepted by the parties but the court ruled that they had been accepted by the defendant, by conduct. Under those terms the adjudicator's fees were payable by the parties, jointly and severally, even if the adjudicator's decision was found to be unenforceable because of a lack of jurisdiction. In the judge's view, both the defendant's reservation of its rights and the relevant clause of the adjudicator's terms permitted the defendant to challenge jurisdiction on enforcement, regardless of the payment of the adjudicator's fees. Even if the judge was wrong on that, in the absence of proper evidence about the basis upon which the fees were paid by the defendant, the judge was not persuaded that the circumstances were sufficiently clear cut in the case to conclude that the defendant had lost the ability to challenge jurisdiction. This was a fact specific issue in this particular case, and should not be seen as authority or encouragement to parties not to follow previous authorities that did not apply in this case.

The defendant did, however, fail in its jurisdictional challenges. In the judge's view, the case was an example of a party "scrabbling around" trying to find reasons not to comply with an adjudicator's decision.

Science and Technology Facilities Council v. MW High Tech Projects UK Ltd [2015] EWHC 2889

3. Supreme Court Takes Another Look at Penalty Clauses – 100 Years On

The Supreme Court has, for the first time since the House of Lords' ruling in 1915, reviewed the law on penalty clauses. In a 110 page judgment, it has decided to keep the rule, but not to extend it. The real question when a contractual provision is challenged as a penalty is, according to the Supreme Court, whether it is penal, not whether it is a pre-estimate of loss. These are not natural opposites or mutually exclusive categories. A damages clause may be neither or both. The fact that the clause is not a pre-estimate of loss does not therefore, at any rate without more, mean that it is penal, and to describe it as deterrent does not add anything.

The true test is whether the impugned provision is a secondary obligation which imposes a detriment on the contract-breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation.

Cavendish Square Holding BV v. Talal El Makdessi [2015] UKSC 67

Originally published 26 November 2015

Learn more about our Asia offices and Construction & Engineering practice.

Visit us at www.mayerbrown.com

Mayer Brown is a global legal services organization comprising legal practices that are separate entities (the Mayer Brown Practices). The Mayer Brown Practices are: Mayer Brown LLP, a limited liability partnership established in the United States; Mayer Brown International LLP, a limited liability partnership incorporated in England and Wales; Mayer Brown JSM, a Hong Kong partnership, and its associated entities in Asia; and Tauil & Chequer Advogados, a Brazilian law partnership with which Mayer Brown is associated. "Mayer Brown" and the Mayer Brown logo are the trademarks of the Mayer Brown Practices in their respective jurisdictions.

© Copyright 2015. The Mayer Brown Practices. All rights reserved.

This article provides information and comments on legal issues and developments of interest. The foregoing is not a comprehensive treatment of the subject matter covered and is not intended to provide legal advice. Readers should seek specific legal advice before taking any action with respect to the matters discussed herein. Please also read the JSM legal publications Disclaimer.